Status Updates

Status Updates

June 22, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of June 22, 2020.
June 8, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of June 8, 2020.
May 25, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of May 25, 2020.
May 11, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of May 11, 2020.
April 27, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of April 27, 2020. We note that we may elect to skip this bi-monthly Site observation walk due to the COVID-19 pandemic.
April 8, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of April 17, 2020. We note that we may elect to skip this bi-monthly Site observation walk due to the COVID-19 pandemic.
March 24, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of March 30, 2020.
March 13, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Collection of waste characterization soil samples proximate to the source removal areas the week of March 9th, 2020 to facilitate the future off-Site disposal of this material. Sampling will be performed by GZA using hand sampling techniques.
  • Completion of the bi-monthly Site observation walk during the week of March 16, 2020.
March 2, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of March 2, 2020.
February 17, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of February 17, 2020.
  • Performance of an additional geotechnical investigation program by BETA as part of the Narragansett Bay Commission’s Phase III Combined Sewer Overflow upgrade project. GZA will provide periodic oversight of the investigation program and will be posting and uploading air monitoring results to the bulletin boards and the project website. The additional investigation work was completed the week of February 10, 2020.
February 3, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of February 3, 2020.
  • Performance of an additional geotechnical investigation program by BETA as part of the Narragansett Bay Commission’s Phase III Combined Sewer Overflow upgrade project. GZA will provide periodic oversight of the investigation program and will be posting and uploading air monitoring results to the bulletin boards and the project website. The additional investigation work is scheduled to start on February 4, 2020.
January 20, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of January 20, 2020.
  • Coordination and performance of an additional geotechnical investigation program by BETA as part of the Narragansett Bay Commission’s Phase III Combined Sewer Overflow upgrade project. GZA will provide periodic oversight of the investigation program and will be posting and uploading air monitoring results to the bulletin boards and the project website. The exact start date has yet to be determined.
January 6, 2020
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of January 6, 2020.
December 2, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of December 9, 2019.
November 18, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of November 25, 2019.
November 4, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of November 11, 2019.
October 21, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of October 28, 2019.
October 7, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of October 14, 2019.
  • Completion of the annual groundwater monitoring the week of October 14, 2019.
September 23, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of September 30, 2019.
September 9, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of September 16, 2019.
  • Continued performance of a geotechnical investigation program by BETA as part of the Narragansett Bay Commission’s Phase III Combined Sewer Overflow upgrade project. Work is anticipated to be completed the week of September 9, 2019. GZA will continue to provide periodic oversight of the investigation program and will be posting and uploading air monitoring results to the bulletin boards and the project website.
  • Performance of invasive plant species management activities within the upland portions of the Site the week of September 16, 2019 consistent with a CRMC Assent.
August 26, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of September 2, 2019.
  • Performance of a geotechnical investigation program by BETA as part of the Narragansett Bay Commission’s Phase III Combined Sewer Overflow upgrade project starting the week of September 2, 2019. GZA will provide periodic oversight of the investigation program and will be posting and uploading air monitoring results to the bulletin boards and the project website.
August 12, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of August 19, 2019.
July 29, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of August 5, 2019.
July 15, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of July 22, 2019.
July 1, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of July 8, 2019.
June 17, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of June 24, 2019.
June 3, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of June 10, 2019.
May 20, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Redevelopment of monitoring well MW-320D the week of May 20, 2019.
  • Completion of the bi-monthly Site observation walk during the week of May 27, 2019.
  • Submittal of the Remedial Action Workplan Addendum the week of May 27, 2019.
May 6, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of test pit investigations to field locate potential submarine electric cables and other former outfalls/pipes the week of May 6, 2019.
  • Completion of the bi-monthly Site observation walk during the week of May 13, 2019.
April 22, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Locating and tracing of below grade utilities using various non-intrusive techniques during the week of April 22, 2019 to facilitate the design of remedy.
  • GZA obtained a Coastal Resource Management Council (CRMC) – Finding of No Significant Impact (FONSI) assent on April 22, 2019 for the performance of additional test pitting activities along the shoreline of the river to evaluate the potential presence of active drain pipes. The test pit activities are currently scheduled for the week of May 6, 2019.
  • Completion of the bi-monthly Site observation walk during the week of April 29, 2019.
April 8, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of April 15, 2019.
March 25, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of April 1, 2019.
  • Completion of a quarterly NAPL gauging and recovery event during the week of April 1, 2019.
March 11, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of March 18, 2019.
February 25, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of March 4, 2019.
February 11, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of February 18, 2019.
January 28, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of February 4, 2019.
January 14, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of January 21, 2019.
  • Completion of quarterly NAPL gauging and recovery the week of January 21, 2019.
December 31, 2019
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of January 7, 2019.
December 17, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of December 24, 2018.
  • Flagging and delineation of wetland soils in the southern and northern portions of the Site.
December 3, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of December 10, 2018.
November 19, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of November 26, 2018.
  • Off-Site disposal of 55-gallon drums of purge water and NAPL generated during groundwater sampling and NAPL recovery activities.
November 5, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Completion of the bi-monthly Site observation walk during the week of November 12, 2018.
  • Locating and tracing of below grade utilities using various techniques during the week of November 12, 2018 to facilitate the design of remedy.
October 10, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of October 15, 2018.
  • complete the quarterly non-aqueous phase liquid (NAPL) gauging round and semi-annual groundwater monitoring round during the week of October 15th.
September 28, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of October 1, 2018.
September 10, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of September 17, 2018.
August 28, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of September 3, 2018.
August 14, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of August 20, 2018.
August 1, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of August 6, 2018.
July 23, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of July 23, 2018.
July 3, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of July 9, 2018.
June 18, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of June 25, 2018.
June 6, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of June 11, 2018.
May 21, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of May 28, 2018.
May 7, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of May 14, 2018.
April 23, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete clearing of a fallen tree on April 25, 2018 to allow access to a monitoring well cluster.
  • Complete the bi-monthly Site observation walk during the week of April 30, 2018.
  • Complete one geotechnical boring between April 30 and May 1, 2018. This boring will be performed directly east of the substation to collect geotechnical information for the design of a new control house being constructed as part of future substation upgrades.
April 9, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of April 16, 2018.
  • Complete quarterly non-aqueous phase liquid gauging and recovery round the week of April 16, 2018.
March 26, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete the bi-monthly Site observation walk during the week of April 2, 2018.
  • On March 28, 2018, a subcontractor engaged by the Narragansett Bay Commission (NBC) will be performing non-intrusive survey work associated with the existing utilities within and proximate to the Site.
March 12, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of March 19, 2018.
February 26, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of March 5, 2018.
February 12, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of February 19, 2018.
January 29, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of February 5, 2018.
January 15, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of January 22, 2018.
January 1, 2018
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of January 8, 2018.
December 17, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of December 25, 2017.
  • Complete limited design investigations (LDI). As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26, 2017, these investigations include performance of test pits, soil borings and the collection and analysis of soil samples. The results of the LDI will be used to facilitate development of the site remedy design. A public notification regarding the LDI activities was issued on August 22, 2017. GZA is performing full time oversight to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan. Air monitoring data is posted on a weekly basis on the Tidewater website (tidewatersite.com) and the bulletin boards located at the end of Tidewater Street and Bowles Court. To date, no exceedances of specified air monitoring limits have been detected. We currently anticipate these investigations will be completed by the end of December 2017.
December 3, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of December 11, 2017.
  • Complete limited design investigations (LDI). As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26, 2017, these investigations include performance of test pits, soil borings and the collection and analysis of soil samples. The results of the LDI will be used to facilitate development of the site remedy design. A public notification regarding the LDI activities was issued on August 22, 2017. GZA is performing full time oversight to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan. Air monitoring data is posted on a weekly basis on the Tidewater website (tidewatersite.com) and the bulletin boards located at the end of Tidewater Street and Bowles Court. To date, no exceedances of specified air monitoring limits have been detected.
November 20, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of November 27, 2017.
  • Continue performance of limited design investigations (LDI). As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26, 2017, these investigations include performance of test pits, soil borings and the collection and analysis of soil samples. The results of the LDI will be used to facilitate development of the site remedy design. A public notification regarding the LDI activities was issued on August 22, 2017. GZA is performing full time oversight to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan. Air monitoring data is posted on a weekly basis on the Tidewater website (tidewatersite.com) and the bulletin boards located at the end of Tidewater Street and Bowles Court. To date, no exceedances of specified air monitoring limits have been detected.
November 6, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of November 13, 2017.
  • Continue performance of limited design investigations (LDI). As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26, 2017, these investigations include performance of test pits, soil borings and the collection and analysis of soil samples. The results of the LDI will be used to facilitate development of the site remedy design. A public notification regarding the LDI activities was issued on August 22, 2017. GZA is performing full time oversight to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan. Air monitoring data is posted on a weekly basis on the Tidewater website (tidewatersite.com) and the bulletin boards located at the end of Tidewater Street and Bowles Court. To date, no exceedances of specified air monitoring limits have been detected.
October 23, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of October 30th.
  •  Continue performance of limited design investigations (LDI). As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26th, 2017, these investigations include performance of test pits, soil borings and the collection and analysis of soil samples. The results of the LDI will be used to facilitate development of the site remedy design. A public notification regarding the LDI activities was issued on August 22nd, 2017. GZA is performing full time oversight to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan. Air monitoring data is posted on a weekly basis on the Tidewater website (tidewatersite.com) and the bulletin boards located at the end of Tidewater Street and Bowles Court. To date, no exceedances of specified air monitoring limits have been detected.
October 9, 2017
SITE ACTIVITIES TO BE PERFORMED

  •  Complete bi-monthly Site observation walk during the week of October 16th.
  •  Continue performance of limited design investigations (LDI). As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26th, 2017, these investigations include performance of test pits, soil borings and the collection and analysis of soil samples. The results of the LDI will be used to facilitate development of the site remedy design. A public notification regarding the LDI activities was issued on August 22nd, 2017. GZA is performing full time oversight to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan. Air monitoring data is posted on a weekly basis on the Tidewater website (tidewatersite.com) and the bulletin boards located at the end of Tidewater Street and Bowles Court. To date, no exceedances of specified air monitoring limits have been detected.
September 25, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of September 25th.
  • Continue performance of limited design investigations (LDI). As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26th, 2017, these investigations include performance of test pits, soil borings and the collection and analysis of soil samples.  The results of the LDI will be used to facilitate development of the site remedy design.   A public notification regarding the LDI activities was issued on August 22nd, 2017.  GZA is performing full time oversight to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan. Air monitoring data is posted on a weekly basis on the Tidewater website (tidewatersite.com) and the bulletin boards located at the end of Tidewater Street and Bowles Court. To date, no exceedances of specified air monitoring limits have been detected.
September 11, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of September 11th.
  • Initiate performance of limited design investigations (LDI).  As described in the Limited Design Investigation Work Plan (LDI Work Plan) submitted to RIDEM on June 26, 2017, these investigations will include performance of test pits, soil borings and the collection and analysis of soil samples.  The results of the LDI will be used in development of the site remedy design.   A public notification regarding the LDI activities was issued on August 22, 2017.  GZA will be on-site full time to manage and document the LDI activities and conduct air quality monitoring consistent with the project-specific Air Quality Monitoring Plan.
August 28, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of September 4th.
  • Continue site reconnaissance and exploration location mark-out during the weeks of August 28th and September 4th for anticipated Limited Design Investigation (LDI) activities.
August 14, 2017
SITE ACTIVITIES TO BE PERFORMED

    • • Complete bi-monthly Site observation walk during the week of August 21st.
    • • Remove the installed silt curtain that associated with the drainage improvements and south washout restoration work on August 17th.
    • Continue site reconnaissance and exploration location mark-out during the weeks of August 14th and 21st for anticipated Limited Design Investigation (LDI) activities.
July 31, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of August 7th.
  • Continue site reconnaissance and exploration location mark-out during the weeks of July 31st and August 7th for anticipated Limited Design Investigation (LDI) activities.
July 17, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of July 24th.
  • Begin site reconnaissance and exploration location mark-out during the week of July 17th for anticipated Limited Design Investigation (LDI) activities.
July 3, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of July 11th.
  • Complete quarterly groundwater and NAPL gauging and NAPL recovery round during the week of July 11th.
June 19, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of June 26th.
June 5, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of June 12th.
May 22, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of May 29th.
May 8, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of May 15th.
April 24, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of May 1st.
April 10, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of April 17th.
  • Complete quarterly groundwater and NAPL gauging and recovery round during the week of April 17th
March 27, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of April 3rd.
March 13, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of March 20th.
February 27, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of March 6th.
February 13, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of February 20th.
January 30, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of February 6th.
January 16, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during the week of January 23rd.
  • Complete quarterly groundwater and NAPL gauging and NAPL recovery round during the week of January 23rd.
January 2, 2017
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of January 9th.
December 19, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of December 19th.
December 5, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of December 12th.
November 21, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of November 28th.
November 7, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of November 14th.
October 24, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of October 24th.
  • Complete quarterly NAPL gauging round and semi-annual groundwater monitoring round during the week of October 24th.
October 10, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of October 10th to 14th, 2016.
September 26, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Anticipate submittal of Short Term Response Action Completion Report – South Washout Area to RIDEM during the week of September 26th, 2016.
  • Complete bi-monthly Site observation walk during week of October 3rd to 7th, 2016.
September 12, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of September 12th to 16th, 2016.
  • Completion of work activities associated with the stormwater system repairs and south washout restoration consistent with the Short Term Response Action Plan (STRAP) which was approved by Rhode Island Department of Environmental Management (RIDEM) on April 19th, 2016. The work was substantially completed during the week of August 22nd, 2016.  Remaining work activities are limited to continued watering planted vegetation and final demobilization of equipment.
August 29, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of August 29th to September 2nd, 2016.
  • Completion of work activities associated with the stormwater system repairs and south washout restoration consistent with the Short Term Response Action Plan (STRAP) which was approved by Rhode Island Department of Environmental Management (RIDEM) on April 19th, 2016. The work was substantially completed during the week of August 22nd, 2016.  Remaining work activities include watering planted vegetation and demobilizing equipment from the Site.
August 15, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of August 15th to 19th, 2016.
  • Continue work activities associated with the stormwater system repairs and south washout restoration work. The work is expected to be substantially completed by August 19th and is being conducted in accordance with a Short Term Response Action Plan (STRAP) which was approved by Rhode Island Department of Environmental Management (RIDEM) on April 19th, 2016. GZA is on-site full time to manage the Contractor, document the STRAP activities, and conduct air monitoring throughout the project. The air monitoring is being performed consistent with the site-specific, RIDEM-submitted Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.  To date, no exceedances of specified air monitoring limits have been detected.
  • As part of the above referenced STRAP, The Narragansett Electric Company is supporting certain activities being performed by the City of Pawtucket associated with their Max Read Field (MRF) reconstruction project. This support involves assistance with excavation, management and transportation of certain excess materials from the MRF project to the Tidewater Site. All excess materials that have been generated to date have been delivered to the Tidewater Site and no additional field soil management support by The Narragansett Electric Company is anticipated.
August 1, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of August 1st to 5th, 2016.
  • Continue work activities associated with the stormwater system repairs and south washout restoration work. The work is expected to be complete by August 19th and is being conducted in accordance with a Short Term Response Action Plan (STRAP) which was approved by Rhode Island Department of Environmental Management (RIDEM) on April 19th, 2016. GZA is on-site full time to manage the Contractor, document the STRAP activities, and conduct air monitoring throughout the project. The air monitoring is being performed consistent with the site-specific, RIDEM-submitted Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.  To date, no exceedances of specified air monitoring limits have been detected.
  • As part of the above referenced STRAP, The Narragansett Electric Company is supporting certain activities being performed by the City of Pawtucket associated with their Max Read Field (MRF) reconstruction project. This support involves  assistance with excavation, management and transportation of certain excess materials from the MRF project to the Tidewater Site.
July 18, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bi-monthly Site observation walk during week of July 25th to July 29th, 2016.
  • Finish mobilization and begin work activities associated with the drainage improvements and south washout restoration work. Earthwork activities are expected to be initiated during the week of July 18th. The work is expected to be complete by August 19th. The work is being conducted in accordance with a Short Term Response Action Plan (STRAP) which was approved by Rhode Island Department of Environmental Management (RIDEM) on April 19th, 2016. GZA will be on-site to manage the Contractor and document the STRAP activities and conduct air monitoring throughout the project. The air monitoring will be consistent with the site-specific, RIDEM-submitted Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.
  • As part of the above referenced STRAP, National Grid will support certain activities being performed by the City of Pawtucket associated with their Max Read Field (MRF) reconstruction project. This support will include assistance with excavation, management and transportation of certain excess materials from the MRF project to the Tidewater Site.
July 4, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of July 4th to 8th, 2016.
  • Mobilize and begin work activities associated with the drainage improvements and south washout restoration work in July 2016. Mobilization is anticipated to start on July 15th with earthwork starting July 18th.  The process is expected to be complete by August 15th. The work is being conducted in accordance with a Short Term Response Action Plan (STRAP) which was approved by Rhode Island Department of Environmental Management (RIDEM) on April 19th, 2016. The Narragansett Electric Company will have a representative on-site who will monitor the work and conduct air monitoring throughout the project. The air monitoring will be consistent with the site-specific, RIDEM-submitted Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.
  • Support work activities being performed by the City of Pawtucket associated with their Max Read Field (MRF) reconstruction project.  The Narragansett Electric Company will have a representative on-site to monitor the City’s work that is planned on a small portion of the Tidewater Site.  Anticipated activities include air monitoring, assistance with soil management including the planned transport of excess materials from the MRF project to the Tidewater Site by the City of Pawtucket.  We understand the City plans to initiate earthwork activities at MRF in mid-July 2016.
June 20, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of June 20th to 24th, 2016.
  • No site activities are planned for the week of June 27th to July 1st, 2016.
June 6, 2016
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of June 6th to 10th, 2016.
  • Complete bimonthly Site observation walk during week of June 13th to 17th, 2016.
May 23, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of May 23rd to May 27th, 2016.
  • No site activities are planned for the week of May 30th to June 3rd, 2016.

National Grid is hosting a public meeting to present the planned upgrades to a storm water system and washout area near the southern end of the  Site. The meeting is scheduled for May 24, 2016 at 6:00 PM at the Francis J. Varieur Elementary School.  A public notification was sent out to the Tidewater mailing list on May 5, 2016.

May 9, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of May 9th to May 13th, 2016.
  • No site activities are planned for the week of May 16th to 20th, 2016.
April 25, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk and perform quarterly NAPL gauging and recovery round during week of April 25th to April 29th, 2016.
  • No site activities are planned for the week of May 2nd to May 6th, 2016.
April 11, 2016
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of April 11th to April 15th, 2016.
  • Complete bimonthly Site observation walk and perform quarterly NAPL gauging and recovery round during week of April 18th to April 22nd, 2016.
March 28, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of March 28th to April 1st, 2016.
  • No site activities are planned for the week of April 4th to April 8th, 2016.
March 14, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of March 14th to March 18th, 2016.
  • No site activities are planned for the week of March 21st to March 25th, 2016.
February 29, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of February 29th to March 4th, 2016.
  • No site activities are planned for the week of March 7th to March 11th, 2016.
February 15, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of February 15th to February 19th, 2016.
  • No site activities are planned for the week of February 22nd to February 26th, 2016.
February 1, 2016
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of February 1st to February 5th, 2016.
  • No site activities are planned for the week of February 8th to February 12th, 2016.
January 18, 2016
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of January 18 to January 22.
  • Complete bimonthly Site observation walk and perform quarterly NAPL gauging and recovery round during week of January 25 to January 29.
January 4, 2016
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of January 4 to January 8, 2016.
  • Complete bimonthly Site observation walk during week of January 11 to January 15, 2016.
December 21, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of December 21 to 25, 2015.
  • Complete bimonthly Site observation walk during week of December 28, 2015 to January 1, 2016.
December 7, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of December 7 to 11, 2015.
  • Complete bimonthly Site observation walk during week of December 14 to 18, 2015.
November 23, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of November 23 to 27, 2015.
  • Complete bimonthly Site observation walk during week of November 30 to December 4, 2015.
November 9, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk, annual groundwater monitoring round and quarterly NAPL gauging round during week of November 9 to 13, 2015.
  • No site activities are planned for the week of November 16 to 20, 2015.
October 26, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of October 26 to 30, 2015.
  • Complete bimonthly Site observation walk, annual groundwater monitoring round and quarterly NAPL gauging round during week of November 2 to 6, 2015.
October 12, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of October 12 to 16, 2015.
  • Complete bimonthly Site observation walk, annual groundwater monitoring round and quarterly NAPL gauging round during week of October 19 to 23, 2015.
September 28, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of September 28 to October 2, 2015.
  • Complete bimonthly Site observation walk during week of October 5 to 9, 2015.
September 14, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of September 14 to 18, 2015.
  • Complete bimonthly Site observation walk during week of September 21 to 25, 2015.
August 31, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Complete a topographical survey of demolition area. The building demolition activities were completed the week of August 24, 2015.
  • Complete bimonthly Site observation walk during week of September 7 to 11, 2015.
August 17, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Complete the demolition activities associated with three on-Site buildings (the former machine shop, purifier house and the meter room).   The work is expected to be complete by August 28th. The Narragansett Electric Company will have a representative on-site who will monitor the work and conduct air monitoring throughout the demolition project. The air monitoring will be consistent with the site-specific, Rhode Island Department of Environmental Management (RIDEM)-approved Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.
  • Complete bimonthly Site observation walk during week of August 17 to 21, 2015.
August 3, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Continue demolition activities associated with three on-Site buildings (the former machine shop, purifier house and the meter room).   The process is expected to be complete by August 28th. The Narragansett Electric Company will have a representative on-site who will monitor the work and conduct air monitoring throughout the demolition project. The air monitoring will be consistent with the site-specific, Rhode Island Department of Environmental Management (RIDEM)-approved Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.
  • Complete bimonthly Site observation walk during week of August 10 to 14, 2015.
July 20, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Continue demolition activities associated with three on-Site buildings (the former machine shop, purifier house and the meter room).   The process is expected to be complete by August 28th. The Narragansett Electric Company will have a representative on-site who will monitor the work and conduct air monitoring throughout the demolition project. The air monitoring will be consistent with the site-specific, Rhode Island Department of Environmental Management (RIDEM)-approved Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.
  • Complete quarterly NAPL gauging round and collection of soil gas sample at SG-105S.
  • Complete bimonthly Site observation walk during week of July 27, 2015 to July 31, 2015.
July 6, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Continue demolition activities associated with three on-Site buildings (the former machine shop, purifier house and the meter room).   The process is expected to be complete by August 28th. The Narragansett Electric Company will have a representative on-site who will monitor the work and conduct air monitoring throughout the demolition project. The air monitoring will be consistent with the site-specific, Rhode Island Department of Environmental Management (RIDEM)-approved Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.
  • Complete bimonthly Site observation walk during week of July 13, 2015 to July 17, 2015.
June 22, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Mobilize and begin demolition activities associated with three on-Site buildings (the former machine shop, purifier house and the meter room) the week of June 22nd.   The process is expected to be complete by August 28th. The Narragansett Electric Company will have a representative on-site who will monitor the work and conduct air monitoring throughout the demolition project. The air monitoring will be consistent with the site-specific, Rhode Island Department of Environmental Management (RIDEM)-approved Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities.
  • Complete bimonthly Site observation walk during week of June 29, 2015 to July 3, 2015.
June 8, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of June 8, 2015 to June 12, 2015.
  • Complete bimonthly Site observation walk during week of June 15, 2015 to June 19, 2015.
  • Mobilize and begin demolition activities associated with three on-Site buildings (the former machine shop, purifier house and the meter room) in June 2015. Mobilization is anticipated to start on June 18th with demolition-related work starting June 23rd.   The process is expected to be complete by August 28th. The Narragansett Electric Company will have a representative on-site who will monitor the work and conduct air monitoring throughout the demolition project. The air monitoring will be consistent with the site-specific, Rhode Island Department of Environmental Management (RIDEM)-approved Air Quality Monitoring Plan that includes a two-tiered approach during intrusive activities. A fact sheet with more information regarding this work will be posted and sent to the email distribution list the week of June 8th.
May 25, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of May 25, 2015 to May 29, 2015.
  • Complete bimonthly Site observation walk during week of June 1, 2015 to June 5, 2015.
May 11, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of May 11, 2015 to May 15, 2015.
  • Complete bimonthly Site observation walk during week of May 18, 2015 to May 22, 2015.
April 27, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Complete quarterly NAPL gauging round and collection of soil gas sample at SG-105S.
  • Complete bimonthly Site observation walk during week of April 27, 2015 to May 1, 2015.
April 13, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of April 13, 2015 to April 17, 2015.
  • Complete bimonthly Site observation walk during week of April 20, 2015 to April 24, 2015.
March 30, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of March 20, 2015 to April 3, 2015.
  • Complete bimonthly Site observation walk during week of April 6, 2015 to April 10, 2015.
March 16, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of March 16, 2015 to March 20, 2015.
  • Complete bimonthly Site observation walk during week of March 23, 2015 to March 27, 2015.
March 2, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of March 2, 2015 to March 6, 2015.
  • Complete bimonthly Site observation walk during week of March 9, 2015 to March 13, 2015.
February 16, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of February 16, 2015 to February 20, 2015.
  • Complete bimonthly Site observation walk during week of February 23, 2015 to February 27, 2015.
February 2, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of February 2, 2015 to February 6, 2015.
  • Complete bimonthly Site observation walk during week of February 9, 2015 to February 13, 2015.
January 16, 2015
SITE ACTIVITIES TO BE PERFORMED

  • Complete quarterly NAPL gauging round and collection of soil gas sample at SG-105S.
  • Complete bimonthly Site observation walk during week of January 26, 2015 to January 30, 2015.
January 5, 2015
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of January 5, 2015 to January 9, 2015.
  • Complete bimonthly Site observation walk during week of January 12, 2015 to January 16, 2015.
December 22, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of December 22 to 26, 2014.
  • Complete bimonthly Site observation walk during week of December 29, 2014 to January 2, 2015.
December 8, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of December 8 to 12, 2014.
  • Complete bimonthly Site observation walk during week of December 15 to 19, 2014.
November  24, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of November 24 to 28, 2014.
  • Complete bimonthly Site observation walk during week of December 1 to 5, 2014.
November  10, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of November 10 to November 14, 2014.
  • Complete bimonthly Site observation walk during week of November 17 to 21, 2014.
October 27 , 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of October 27 to October 31, 2014.
  • Complete bimonthly Site observation walk during week of November 3 to 7, 2014.
October 13, 2014
SITE ACTIVITIES TO BE PERFORMED

  • Continue material and debris removal from the three Site buildings. We currently expect that this work will be completed by October 17, 2014. No soil will be disturbed as part of this activity.
  • Complete quarterly NAPL gauging round and collection of soil gas sample at SG-105S.
  • Complete bimonthly Site observation walk during week of October 20 to 24, 2014.
September 29, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of September 29 to October 3, 2014.
  • Complete bimonthly Site observation walk during week of October 6 to 10, 2014.
  • Materials and debris will be removed from  three Site buildings starting on  October 6, 2014. We currently expect this work will take approximately 2 weeks to complete and also include limited brush cutting and clearing around the buildings. No soil will be disturbed as part of this activity.
September 15, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of September 15 to 19, 2014.
  • Complete bimonthly Site observation walk during week of September 22 to 26, 2014.
September 1, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of September 1 to 5, 2014.
  • Complete bimonthly Site observation walk during week of September 8 to 12, 2014.
August 18, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of August 18 to 22, 2014.
  • Complete bimonthly Site observation walk during week of August 25 to 29, 2014.
August 4, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of August 4 to 8, 2014.
  • Complete bimonthly Site observation walk during week of August 11 to 15, 2014.
July 21, 2014
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of July 21 to 25, 2014.
  • Complete quarterly NAPL gauging round and collection of soil gas sample at SG-105S. Results of the soil gas sampling and testing will be summarized in a brief memo for submittal to the Rhode Island Department of Environmental Management (RIDEM). It is anticipated that this memo will be submitted to RIDEM in late August/early September.
July 7, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of July 7 to 11, 2014.
  • Complete bimonthly Site observation walk during week of July 14 to 18, 2014.
June 23, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of June 23 to 27, 2014.
  • Complete bimonthly Site observation walk during week of June 30 to July 4, 2014.
June 9, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of June 9 to 13, 2014.
  • Complete bimonthly Site observation walk during week of June 16 to 20, 2014.
May 26, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of May 26 to 30, 2014.
  • Complete bimonthly Site observation walk during week of June 2 to 6, 2014.
May 12, 2014
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of May 12 to 16, 2014.
  • No site activities are planned for the week of May 19 to 23, 2014.
April 28, 2014
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of April 28 to May 2, 2014.
  • No site activities are planned for the week of May 5 to 9, 2014.
April 14, 2014
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of April 14 to 18, 2014.
  • Complete quarterly NAPL gauging round and groundwater sampling for the newly installed wells within the natural gas regulator station area during the week of April 14 to 18, 2014. We currently expect these activities to take 2 days to complete.
  • No site activities are planned for the week of April 21 to 25, 2014.
March 31, 2014
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly Site observation walk during week of March 31 to April 4, 2014.
  • Perform drilling activities related to the limited soil and groundwater investigation program within the natural gas regulator station. These investigations are designed to further evaluate results of the soil gas testing recently performed near the natural gas regulator station.  We currently expect drilling activities will be initiated during the week of March 31, 2014 and will take 2 to 3 days to complete.  A public notification regarding the proposed investigation was distributed on February 21, 2014.
March 17, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of March 17 to 21, 2014.
  • Complete bimonthly Site observation walk during week of March 24 to 28, 2014.
  • Perform drilling activities related to the limited soil and groundwater investigation program within the natural gas regulator station. These investigations are designed to further evaluate results of the soil gas testing recently performed near the natural gas regulator station.  We currently expect drilling activities will be initiated during the week of March 24, 2014, depending on weather and snow cover and will take 2 to 3 days to complete.  A public notification regarding the proposed investigation was distributed on February 21, 2014.
March 3, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No site activities are planned for the week of March 3 to 7, 2014.
  • Complete bimonthly Site observation walk during week of March 10 to 14, 2014.
  • Perform drilling activities related to the limited soil and groundwater investigation program within the natural gas regulator station. These investigations are designed to further evaluate results of the soil gas testing recently performed near the natural gas regulator station.  We currently expect drilling activities will be initiated on or about March 10, 2014, depending on weather and snow cover and will take 2 to 3 days to complete.  A public notification regarding the proposed investigation was distributed on February 21, 2014.

National Grid is hosting a public meeting to present the results of the recently competed soil gas testing at  the Tidewater Site. In addition to The Narragansett Electric Company, representatives of RIDEM and EPA will attend.  The meeting is scheduled for March 6, 2014 from 6:30 to 7:30 PM at the Francis J. Varieur Elementary School. The end of the meeting will be extended if necessary to answer any questions.  A public notification was sent out to the Tidewater mailing list on February 11, 2014.

February 17, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for the week of February 17 to 21, 2014.
  • Complete bimonthly Site observation walk during week of February 24 to 28, 2014.
  • Complete a bid walk on February 25, 2014 with drilling subcontractors for the upcoming limited soil and groundwater investigation. A Supplementation Site Investigation Work Plan (SSIWP) describing the proposed investigations was submitted to the Rhode Island Department of Environmental Management (RIDEM) Office of Waste Management in February 2014. A copy of the SSIWP can be found on The Narragansett Electric Company’s Tidewater website (www.tidewatersite.com).

National Grid is holding a public meeting to present the results of the soil gas testing completed by Narragansett Electric Company at the Tidewater Site. The meeting is scheduled for March 6, 2014 from 6:30 to 7:30 PM at the Francis J. Varieur Elementary School. A public notification was sent out to the Tidewater mailing list on February 11, 2014.

February 3, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for the week of February 3 to 7, 2014.
  • Complete bimonthly Site observation walk during week of February 10 to 14, 2014.

National Grid is in the process of coordinating a public meeting to present the results of the soil gas testing completed by Narragansett Electric Company at the Tidewater Site. It is anticipated that the meeting will be held in early March 2014. A public notification will be sent out to the Tidewater mailing list a minimum of two weeks prior to the meeting date once the final date is confirmed.

January 20, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for the week of January 20 to 24, 2014.
  • Complete bimonthly Site observation walk during week of January 27 to 31, 2014.
January 6, 2014
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for the week of January 6 to 10, 2014.
  • Complete bimonthly Site observation walk during week of January 13 to 17, 2014.

Going forward, status reports will be provided on a bimonthly basis (i.e., once every two weeks).

December 23, 2013
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for the week of December 23 to 27, 2013.
  • Complete bimonthly Site observation walk during week of December 30, 2013 to January 3, 2014.

Excavation and aboveground work associated with the electrical substation upgrades is complete.

December 16, 2013
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for this week.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

December 9, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly site observation walk.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

December 2, 2013
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for this week.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

November 25, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete bimonthly site observation walk.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

November 18, 2013
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for this week.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

November 11, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk. Going forward, this activity will be performed on a bimonthly basis.
  • Install protective casings for previously installed soil gas probes.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

November 4, 2013
SITE ACTIVITIES TO BE PERFORMED

  • No activities are planned for this week.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

October 28, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Perform quarterly NAPL and groundwater gauging and recovery round.

Excavation associated with the substation upgrades is complete. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

October 21, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Perform paving activities around the natural gas regulator station.

Excavation associated with the substation upgrades is complete. No transient or sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week. The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

October 14, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Perform minor excavation work associated with an on-site utility conduit.

Minor excavation (associated with utility conduit) is planned for the week of October 13, 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards and Narragansett Electric Company Tidewater website (www.tidewatersite.com) prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

October 7, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A complete report describing the recent soil gas sampling and analyses was submitted to RIDEM on October 2, 2013. A copy of the report is available on the Narragansett Electric Company Tidewater website (www.tidewatersite.com). Minor excavation (associated with utility conduit) is planned for the week of October 13, 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards and Narragansett Electric Company Tidewater website (www.tidewatersite.com) prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

September 30, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A complete report describing the recent soil gas sampling and analyses is currently being prepared and will be submitted to RIDEM the week of September 30, 2013. Minor excavation (associated with utility conduit) is planned for the week of October 13, 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards and Narragansett Electric Company Tidewater website (www.tidewatersite.com) prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings. It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

September 23, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A summary of the recently collected soil gas data was posted on the Tidewater website (www.tidewatersite.com) and provided to RIDEM on August 28, 2013.  Translated versions of the summary are also available on the website.  A complete report describing the soil gas sampling and analyses is currently being prepared and will be submitted to RIDEM in late September 2013.

September 16, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A summary of the recently collected soil gas data was posted on the Tidewater website (www.tidewatersite.com) and provided to RIDEM on August 28, 2013.  Translated versions of the summary are also available on the website.  A complete report describing the soil gas sampling and analyses is currently being prepared and will be submitted to RIDEM in late September 2013.

September 9, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A summary of the recently collected soil gas data was posted on the Tidewater website (www.tidewatersite.com) and provided to RIDEM on August 28, 2013.  Translated versions of the summary are also available on the website.  A complete report describing the soil gas sampling and analyses is currently being prepared and will be submitted to RIDEM in mid- to late September 2013.

September 2, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A summary of the recently collected soil gas data was posted on the Tidewater website (www.tidewatersite.com) and provided to RIDEM on August 28, 2013. A complete report describing the soil gas sampling and analyses is currently being prepared and will be submitted to RIDEM in mid- to late September 2013.

August 26, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A report describing the recent soil gas sampling and analyses is currently being prepared and will be submitted to RIDEM in mid September 2013. In advance of this report, National Grid will provide RIDEM a summary of the soil gas data.  We currently anticipate this data summary will be submitted to RIDEM by August 29, 2013.

August 19, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

A report summarizing the recent soil gas sampling and analyses will be prepared and submitted to RIDEM. It is currently anticipated that the summary report will be submitted to RIDEM in September 2013.

August 12, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

Soil gas sampling activities are complete. A report summarizing the soil gas sampling and analyses will be prepared and submitted to RIDEM. It is currently anticipated that the summary report will be submitted to RIDEM in September 2013.

August 5, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Perform annual groundwater sampling and NAPL gauging event.

Soil gas sampling activities are complete. A report summarizing the soil gas sampling and analyses will be prepared and submitted to RIDEM. It is currently anticipated that the summary report will be submitted to RIDEM in early September 2013.

July 29, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue soil gas probe sampling.

Soil gas sampling will be performed consistent with the May 2013 Supplemental Site Investigation Work Plan (SSIWP). It is currently anticipated that the soil gas sampling will be completed during the week of July 29, 2013.

July 22, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Sample soil gas probes.

Soil gas sampling will be performed consistent with the May 2013 Supplemental Site Investigation Work Plan (SSIWP). It is currently anticipated that the soil gas sampling will be completed over an approximate two week time period.

July 15, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

Field work to install the probes associated with the soil gas quality survey was completed between July 8 and 11, 2013. During the soil gas probe installation, ambient air monitoring was performed consistent with the May 2013 SSIWP. This monitoring included Total Volatile Organic Compounds (TVOCs) and particulate dust in the work zone perimeter. No transient or sustained threshold values were noted for either TVOCs or dust during the air monitoring this past week. The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. It is currently anticipated that the probes will be sampled during the week of July 22, 2013.

July 8, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Installation of soil gas probes associated with soil gas quality survey.

The soil gas quality survey will be performed in accordance with the Supplemental Site Investigation Work Plan (SSIWP) which was submitted to RIDEM on May 2, 2013. During the soil gas probe installation, ambient air monitoring will be performed consistent with the May 2013 SSIWP. This monitoring will include Total Volatile Organic Compounds (TVOCs) and particulate dust in both the worker breathing zone and the work zone perimeter. The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards on a weekly basis.   It is currently anticipated that the probes will be sampled during the week of July 22, 2013.

July 1, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013. GZA anticipates starting the field work associated with the soil gas survey the week of July 8, 2013.

June 24, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

June 17, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

June 10, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

June 3, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013. Upgrades to the interior of the natural gas regulator buildings are scheduled between May 31, 2013 and June 4, 2013.

May 27, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013. Upgrades to the interior of the natural gas regulator buildings are scheduled between May 31, 2013 and June 4, 2013.

May 20, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

May 13, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013.

May 6, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

April 29, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for October 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

April 22, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for May 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

April 15, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for May 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

April 8, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for May 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

April 1, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for May 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

March 25, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for May 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

March 18, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for May 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

March 11, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades is complete. Minor excavation (associated with electrical conduit) is planned for May 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Air monitoring during excavation was performed on March 5 and 6, 2013.  No transient or sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week. The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday.

March 4, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue minor earthwork associated with the proposed electrical substation upgrades.

The majority of the earthwork associated with the substation upgrades was completed in January 2013. Minor excavation (associated with fence installation around the substation and electrical conduit) is planned for late February/early March 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. No transient or sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week. The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday.

February 25, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue minor earthwork associated with the proposed electrical substation upgrades.

The majority of the earthwork associated with the substation upgrades was completed in January 2013. Minor excavation (associated with fence installation around the substation and electrical conduit) is planned for late February/early March 2013. The color-coded alert system indicating when excavation is active (yellow sheet) and not active (blue sheet) will be updated on the bulletin boards prior to the start of the minor excavation work. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted.

February 18, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades was completed in January 2013. Minor excavation (associated with fence installation around the substation) is planned for late February 2013. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in February 2013. This work consists of aboveground work and will not involve soil excavation.

February 11, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

The majority of the earthwork associated with the substation upgrades was completed in January 2013. Minor excavation (associated with fence installation around the substation) is planned for late February 2013. GZA will continue to oversee soil management and conduct air monitoring during these earth disturbing activities. Air monitoring will be performed consistent with the summary memorandum which was submitted to RIDEM on September 28, 2012. The remainder of the work associated with the electrical substation upgrade project will consist of aboveground work within the substation and buildings.  It is currently anticipated that the aboveground work associated with the substation upgrades will continue until the end of July 2013. No sustained or transient threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week.  The air monitoring data will be posted on the National Grid website and the site bulletin boards by Monday. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in February 2013. This work consists of aboveground work and will not involve soil excavation.

February 4, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue earthwork associated with the proposed electrical substation upgrades (fence post installations).

Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program being implemented during earthwork activities associated with the on-going electrical substation upgrade project was submitted to RIDEM on September 28, 2012. Earthwork associated with the electrical substation project was not performed during the past week; therefore no air monitoring data will be posted. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in February 2013. This work consists of aboveground work and will not involve soil excavation.

January 28, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Complete quarterly NAPL gauging and recovery round.
  • Continue earthwork associated with the proposed electrical substation upgrades.

During the substation earthwork activities, air monitoring is being performed as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program being implemented during earthwork activities associated with the on-going electrical substation upgrade project was submitted to RIDEM on September 28, 2012. No transient or sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week.  The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in January 2013. This work consists of aboveground work and will not involve soil excavation.

January 21, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Complete quarterly NAPL gauging and recovery round.
  • Continue earthwork associated with the proposed electrical substation upgrades.

During the substation earthwork activities, air monitoring is being performed as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program being implemented during earthwork activities associated with the on-going electrical substation upgrade project was submitted to RIDEM on September 28, 2012. No transient or sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week.  The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in January 2013. This work consists of aboveground work and will not involve soil excavation.

January 14, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue earthwork associated with the proposed electrical substation upgrades.

During the substation earthwork activities, air monitoring is being performed as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program being implemented during earthwork activities associated with the on-going electrical substation upgrade project was submitted to RIDEM on September 28, 2012. No sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week. No transient threshold values were observed for dust; however, on January 8, 2012, a transient threshold exceedance was noted for TVOCs which was noted to be likely attributable to a neighboring resident managing their trash. The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in January 2013. This work consists of aboveground work and will not involve soil excavation.

January 7, 2013
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue earthwork associated with the proposed electrical substation upgrades.

During the substation earthwork activities, air monitoring is being performed as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program being implemented during earthwork activities associated with the on-going electrical substation upgrade project was submitted to RIDEM on September 28, 2012. No sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week.  The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in early January 2013. This work consists of aboveground work and will not involve soil excavation.

December 31, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue earthwork associated with the proposed electrical substation upgrades.

During the substation earthwork activities, air monitoring is being performed as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program being implemented during earthwork activities associated with the on-going electrical substation upgrade project was submitted to RIDEM on September 28, 2012. No sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week.  The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in early January 2013. This work consists of aboveground work and will not involve soil excavation.

December 24, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue earthwork associated with the proposed electrical substation upgrades.

During the substation earthwork activities, air monitoring is being performed as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program being implemented during earthwork activities associated with the on-going electrical substation upgrade project was submitted to RIDEM on September 28, 2012. No sustained threshold values were noted for either total volatile organic compounds (TVOCs) or dust during the air monitoring this past week.  The air monitoring data will be posted on the Narragansett Electric Company website and the site bulletin boards by Monday. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in December 2012. This work consists of aboveground work and will not involve soil excavation.

December 17, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continued mobilization of Contractor equipment to the Site associated with the electrical substation project.
  • Begin earthwork associated with the proposed electrical substation upgrades.

Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program which will be implemented during earthwork activities associated with the upcoming electrical substation upgrade project was submitted to RIDEM on September 28, 2012. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in December 2012. This work consists of aboveground work and will not involve soil excavation.

December 10, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continued mobilization of Contractor equipment to the Site associated with the electrical substation project.
  • Begin earthwork associated with the proposed electrical substation upgrades.

Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program which will be implemented during earthwork activities associated with the upcoming electrical substation upgrade project was submitted to RIDEM on September 28, 2012. Replacement of the meter building associated with natural gas regulator station is ongoing and is expected to be completed in December 2012. This work consists of aboveground work and will not involve soil excavation.

November 26, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Mobilization of Contractor equipment to the Site associated with the electrical substation project.

Due to the recent storms, earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin the week of December 3 or 10, 2012. Notification of the actual start date will be posted on the Narragansett Electric Company website (wwww.tidewatersite.com) and the bulletin boards at the end of Tidewater Streetand Bowles Court. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program which will be implemented during earthwork activities associated with the upcoming electrical substation upgrade project was submitted to RIDEM on September 28, 2012. Once the earthwork activities begin at the Site associated with the electrical substation upgrades, status report updates will be provided on a weekly basis. Replacement of the meter building associated with natural gas regulator station is currently planned for the week of November 26, 2012. This work consists of aboveground work and will not involve soil excavation. Equipment associated with the building replacement work, including a crane, may be mobilized to the Site during the reporting period.

November 11, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Mobilization of Contractor equipment to the Site associated with the electrical substation project.

Due to the recent storms, earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin the week of November 26, 2012. Notification of the actual start date will be posted on the Narragansett Electric Company website (wwww.tidewatersite.com) and the bulletin boards at the end of Tidewater Streetand Bowles Court. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program which will be implemented during earthwork activities associated with the upcoming electrical substation upgrade project was submitted to RIDEM on September 28, 2012. Once the earthwork activities begin at the Site associated with the electrical substation upgrades, status report updates will be provided on a weekly basis. Replacement of the meter building associated with natural gas regulator station is currently planned for the end of November 2012. This work consists of aboveground work and will not involve soil excavation. Equipment associated with the building replacement work, including a crane, may be mobilized to the Site during the reporting period.

October 29, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Mobilization of Contractor equipment to the Site associated with the electrical substation project.

Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin the week of November 5, 2012. Notification of the actual start date will be posted on the Narragansett Electric Company website (wwww.tidewatersite.com) and the bulletin boards at the end of Tidewater Street and Bowles Court. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012.  On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program which will be implemented during earthwork activities associated with the upcoming electrical substation upgrade project was submitted to RIDEM on September 28, 2012. Once the earthwork activities begin at the Site associated with the electrical substation upgrades, status report updates will be provided on a weekly basis. Replacement of the meter building associated with natural gas regulator station is currently planned for early November 2012. This work consists of aboveground work and will not involve soil excavation. Equipment associated with the building replacement work, including a crane, may be mobilized to the Site during the reporting period.

October 15, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin the week of November 5, 2012. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012. On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program which will be implemented during earthwork activities associated with the upcoming electrical substation upgrade project was submitted to RIDEM on September 28, 2012. In order to keep the public informed of the excavation activities and the associated air monitoring for the proposed electrical substation work, bulletin boards have been installed at the end of Tidewater Street and Bowles Court. Air monitoring data will be posted to the bulletin boards on a weekly basis. In addition, The Narragansett Electric Company has established a website for the Site (www.tidewatersite.com). This website will provide the public with updates on current and proposed activities at the Site. Replacement of the meter building associated with natural gas regulator station is currently planned for early November 2012. This work consists of aboveground work and will not involve soil excavation.

October 1, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin the week of October 22, 2012. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012. On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. A summary memorandum of the air quality monitoring program which will be implemented during earthwork activities associated with the upcoming electrical substation upgrade project was submitted to RIDEM on September 28, 2012. In order to keep the public informed of the excavation activities and the associated air monitoring for the proposed electrical substation work, bulletin boards have been installed at the end of Tidewater Street and Bowles Court. Air monitoring data will be posted to the bulletin boards on a weekly basis. Replacement of the meter building associated with natural gas regulator station is currently planned for early November 2012. This work consists of aboveground work and will not involve soil excavation.

September 17, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Perform limited clearing of vegetation along select transmission line corridors.

Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin the week of October 1, 2012. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012. On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. Replacement of the meter building associated with natural gas regulator station is currently planned for mid October 2012. This work consists of aboveground work and will not involve soil excavation.

September 3, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin the week of September 17, 2012. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012. On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required. Replacement of the meter building associated with natural gas regulator station is currently planned for mid October 2012. This work consists of aboveground work and will not involve soil excavation.

August 6, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin in September 2012. Air monitoring will be performed during the earthwork activities as described in GZA’s February 20, 2012 Evaluation of Applicability of Air Pollution Control Regulation No. 9 submittal to the RIDEM Office of Air Resources and GZA’s subsequent correspondence with RIDEM dated June 14, 2012 and July 27, 2012. On July 5, 2012, RIDEM issued a letter stating that an air permit for these proposed earthwork activities would not be required.

July 23, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.

Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin in September 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

July 9, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Complete annual groundwater and NAPL monitoring round.

The excavation work associated with the regulator station upgrades is complete. Above-ground work associated with the regulator station is complete, except for replacement of one of the buildings within the regulator station fence line. The schedule for this work is currently being evaluated. Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin in August 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

June 25, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Complete limited emergency earthwork associated with repair of water line located immediately south of the natural gas regulator station. During earthwork activities, air monitoring will be performed by GZA consistent with the RIDEM approved, April 2011 Air Quality Monitoring Program (AQMP) and subsequent May 5, 2011 correspondence.  We currently anticipate this limited repair will be completed in one to two days and will involve a minimal amount of soil disturbance (approximately 10 cubic yards). It is anticipated that excavated material will be reused as backfill and no soil will be transported off-site.

The excavation work associated with the regulator station upgrades is complete. Above-ground work associated with the regulator station is complete, except for replacement of one of the buildings within the regulator station fence line. The schedule for this work is currently being evaluated. Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin in August 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

June 11, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Complete limited emergency earthwork associated with repair of water line located immediately south of the natural gas regulator station. During earthwork activities, air monitoring will be performed by GZA consistent with the RIDEM approved, April 2011 Air Quality Monitoring Program (AQMP) and subsequent May 5, 2011 correspondence.  We currently anticipate this limited repair will be completed in one to two days and will involve a minimal amount of soil disturbance (approximately 10 cubic yards). It is anticipated that excavated material will be reused as backfill and no soil will be transported off-site.

The excavation work associated with the regulator station upgrades is complete. Above-ground work associated with the regulator station is complete, except for replacement of one of the buildings within the regulator station fence line. The schedule for this work is currently being evaluated. Earthwork associated with the proposed electrical substation upgrades is currently anticipated to begin in August 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

May 28, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Continue the assessment of the conditions of the remaining three buildings located on the Former Manufactured Gas Plant Area (FGPA) portion of the Site.  This assessment will be used by The Narragansett Electric Company as part of an evaluation to raze these historic structures. This work is tentatively scheduled to be performed on June 1, 2012.

The excavation work associated with the regulator station upgrades is complete. Above-ground work associated with the regulator station is complete, except for replacement of one of the buildings within the regulator station fence line. The schedule for this work is currently being evaluated. Earthwork associated with the proposed electrical substation upgrades is tentatively anticipated to begin in August 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

May 14, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Complete fence repair along northern property boundary.
  • Perform an assessment of the conditions of the remaining three buildings located on the Former Manufactured Gas Plant Area (FGPA) portion of the Site.  This assessment will be used by The Narragansett Electric Company as part of an evaluation to raze these historic structures. This work is tentatively scheduled to be performed on May 17, 18 and 21, 2012.

The excavation work associated with the regulator station upgrades is complete. Above-ground work associated with the regulator station is complete, except for replacement of one of the buildings within the regulator station fence line. The schedule for this work is currently being evaluated. Earthwork associated with the proposed electrical substation upgrades is tentatively anticipated to begin in August 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

April 30, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Complete fence repair along northern property boundary.

The excavation work associated with the regulator station upgrades is complete. Above-ground work associated with the regulator station is complete, except for replacement of one of the buildings within the regulator station fence line. The schedule for this work is pending. Earthwork associated with the proposed electrical substation upgrades is tentatively anticipated to begin in August 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

April 16, 2012
SITE ACTIVITIES TO BE PERFORMED

  • Complete site observation walk.
  • Perform quarterly NAPL gauging and recovery round.

The excavation work associated with the regulator station upgrades is complete. Above-ground work associated with the regulator station is complete, except for replacement of one of the buildings within the regulator station fence line. The schedule for this work is pending. Earthwork associated with the proposed electrical substation upgrades is tentatively anticipated to begin in August 2012. An evaluation regarding the applicability of Air Pollution Control Regulation No. 9 with respect to the excavation work associated with proposed electrical substation upgrades was submitted to RIDEM on February 13, 2012.

[/column]

About Status Updates The Narragansett Electric Company currently provides updates on a biweekly and monthly basis for the Rhode Island Department of Environmental Management (RIDEM) concerning activities and developments related to the environmental remediation of the site. If you would like to download PDFs of the original documentation, please click here.